FIRST DIVISION
OFFICE OF THE OMBUDSMAN, G.R. No. 169029
Petitioner,
Present:
PANGANIBAN,
C.J., Chairperson,
YNARES-SANTIAGO,
- versus- AUSTRIA-MARTINEZ,
CALLEJO, SR., and
CHICO-NAZARIO, JJ.
ROGELIO Q. TONGSON, SANNY
BOY O. OROPEL, JAIME S.J.
JAVELLANA, JOSE C.
MARAVILLA,
and COURT OF APPEALS-CEBU
(Former Eighteenth Division), Promulgated:
Respondents.
x-----------------------------------------------------------------------------------------x
CALLEJO, SR., J.:
Assailed before the Court in this Petition for Review is
the Decision[1] of the
Court of Appeals (CA) in CA-G.R. SP No. 84694, reversing the March 8, 2004 Decision
and May 7, 2004 Order of the Office of the Ombudsman (Visayas), as well as the
Resolution denying the motion for reconsideration thereof.
The
Republic of the P14,582,000.00.[2]
On May 15, 2000, respondent Rogelio Q. Tongson, DPWH District
Engineer, 1st Negros Occidental Engineering District, issued a notice of award[3] to
Korona Construction (“Korona” for brevity) for the concreting of the said Bacolod
City-Murcia-D.S. Benedicto-San Carlos City National Road, Murcia Section,
Murcia, Negros Occidental for the price of P13,457,350.00. Ciro Y. King, the sole proprietor of Korona,
conformed to the award on
Under the contract, Korona had to complete the project in 297 calendar days from receipt of notice to commence work, as follows:
ITEM NO. |
DESCRIPTION |
UNIT |
QUANTITY |
UNIT COST |
TOTAL |
105 |
Subgrade
preparation |
Sq.m. |
24,912.36 |
11.61 |
|
202 |
Crushed
Aggregate Base Course |
Cu.m. |
5,862.00 |
292.20 |
1,712,876.40 |
311 |
Portland
Cement Concrete Pavement |
Sq.m. |
19,566.36 |
562.01 |
10,996,489.98 |
Spl. Item |
Roadway
shoulder |
Cu.m. |
1,447.00 |
316.96 |
458,641.12 |
TOTAL |
|
|
|
|
|
To guarantee faithful compliance with the terms and
conditions of the contract, King obliged himself to post a performance bond,
10% of the contract price, and a security bond from the GSIS equivalent to 10%
of the contract cost immediately after the project shall have been 100% completed.
These bonds would answer for any defects that may arise out of the project within
the period of one year.[6] The plans and specifications, as well as the
general and special conditions and Certificate of Site Inspection were deemed
to be part of the contract.[7] The performance bond was thereafter posted.
On P2,018,586.00 or 15% of the contract
price as mobilization.[9] Per Accomplishment Report dated P1,844,253.58.[12]
On
recommendation of Maravilla and Javellana,[15]
which was thereafter approved by Oropel.
Forthwith, Maravilla and Javellana issued a
certificate of project completion.[16] On
P672,862.00.[17] Oropel,
Maravilla, Javellana and Tongson approved King’s Disbursement Voucher[18] for
the full payment of the uncollected contract price. With the authority of Oropel and Tongson, King
was paid the balance of the contract price, less value-added tax and
withholding tax in the amount of P608,634.27.[19] However, it turned out that, as of
On
In a letter[22] dated
On
November 7, 2002, Chan executed an Affidavit-Complaint[24] charging Tongson, Oropel, Javellana and
Maravilla with “possible violation of (our) anti-graft law, falsification of
official document, unethical conduct of public officers, dishonesty, and grave
misconduct by taking advantage of their official functions and conspiring and
confederating with each other in an attempt to defraud the government in the
implementation of government projects, were it not for the timely discovery of
the anomaly.”[25] The
complaint was then filed before the Office of the Ombudsman (Visayas). Chan
asserted that the respondent engineers had made untruthful statements in their
accomplishment reports, reports of inspection and certificates of project
completion, which led to the premature full payment of the contract price. Chan
claimed that Tongson instructed Oropel to resume construction and fast track
the completion of the project only after the controversy had been reported to the
media.
Chan also asserted that there was no
legal reason why the respondents should not be charged and found guilty of
violating Section 3(e), Republic Act No. 3019, considering Oropel’s admission
in his letter to the Graftwatch that the full payment was released for a
project which was not yet completed. Thus, respondents committed falsification
of public documents when they caused Mayor Coscocuella to sign the certificate
of turn-over and acceptance of the project of the city. Chan, likewise, sent a
letter[26]
dated
The Office
of the Ombudsman considered the Affidavit-Complaint as charges against the
respondents for violation of Section 3(e), Rep. Act No. 3019, and Malversation
under Article 217 of the Revised Penal Code.
The case was docketed as OMB-V-C-02-0710-K. The complaint was also
considered an administrative complaint for dishonesty arising from the criminal
complaint, docketed as OMB-V-A-02-0614-K.
In his Counter-Affidavit, Tongson
averred that the case had been mooted by the completion of the project. He admitted that when he approved the accomplishment
report on
Tongson asserted that the complaint against him and the
others was filed by Chan because the latter, not being a duly licensed or
accredited contractor/supplier, had not been awarded any project by the Office
of the District Engineer. Chan had also violated the rule on forum-shopping
because he had likewise filed a complaint[27]
in November 2002 against the respondents with the Secretary of the DPWH based
on the same facts. The DPWH Fact-Finding Team, however, recommended that the
complaint be dismissed and the case terminated on
Oropel submitted his Counter-Affidavit[30] where
he adopted the claims of respondent Tongson. He added, however, that it is a
common practice in the construction industry to consider a project that is 95%
complete as substantially completed; a list containing the remaining work is
thereafter prepared, indicating the time of completion, among others. He
reiterated then that it is not unusual to process the full payment of the
contractor. He emphasized further that the contractor was paid because of his
honest belief that the project was to end at
Javellana and Maravilla, in their Joint Counter-Affidavit,[31]
asserted, among others, that they did not make untruthful statements in their
In his Affidavit, King declared that when the respondents
released the 10% retention money, he was informed that the project had not yet been
completed because the length of the project was short of what was stipulated in
the contract. He and some DPWH officers conducted a resurvey and found that the
road length fell short by 1,341.72 sq m. Hence, it was decided that a portion
of the Lopez Jaena Section located more than one km. away from the bridge, the
terminal of the project, would be concreted. He immediately commenced the work
and completed it in May 2002.
Meantime, on
On
On
In his decision, the Ombudsman
approved the recommendation of the Prosecution Officer, declaring that
evidently, respondent Engr. Jose C. Maravilla and Engr. Jaime S.J. Javellana,
on orders of their supervisors District Engineer Rogelio Q. Tongson and Asst.
District Engineer Sanny Boy Oropel, inspected the work accomplishments of King
and reported that the project had been completed, but it turned out that the
project was still 20% deficient. They admitted that there was an error in the
computation of the area coverage of the project from the
WHEREFORE, District
Engineer Rogelio Q. Tongson, Asst. District Engineer Sanny Boy Oropel, Engineer
III James S.J. Javellana, and Engineer II Jose C. Maravilla are hereby found
administratively liable for Conduct Prejudicial to the Best Interest of the
Service. They are hereby meted the PENALTY OF SIX MONTH SUSPENSION without pay,
with the warning that a repetition of a similar offense will be dealt with more
severely.
However, PBAC Member Nila M. Guanco, Administrative
Officer Rogelio S. Bat-og, Materials Quality Control Head Rodolfo J. Baguiro,
Materials Quality Control Technician Pedrito L. Padadasaba, Acting Accountant
Mary Jane N. Herida, and Internal Control Unit Officer Marvel V. Macainan, are
exonerated from the charge as they did not have any hand in the inspection of
the work accomplishment of the project. Likewise exonerated is State Auditor
III Alfredo O. Carisma as he likewise has no involvement in the matter.[36]
The
complainant filed a Motion for Reconsideration of the Ombudsman’s resolution
dismissing the criminal complaint. Respondents likewise filed a Motion for Reconsideration,[37] averring
that the 5.60% deficiency on the project was a simple oversight. Respondents’ motion was denied on
Petitioners
filed a petition for review before the CA, assailing the
In
light of the over-all (sic) backdrop of the case, We hold to GRANT the petition
for review and the 8 March 2004 Decision
and 7 May 2004 Order of the Office of the Ombudsman (Visayas)
finding the petitioners administratively liable for Conduct Prejudicial to the
Best Interest of the Service and suspending them for a period of six (6) months
without pay are REVERSED and SET ASIDE.
Consequently,
the bond posted by petitioners to answer for any damages that may be sustained
by respondents by reason of the injunctive relief issued by the Court in its Resolution of
The
Office of the Ombudsman filed its Motion for Reconsideration[43] on
The
Office of the Ombudsman filed with this Court a petition for review on certiorari[45]
under Rule 45, questioning the Decision and Resolution of the CA on the
following grounds:
I.
WITH ALL DUE RESPECT, THERE IS MORE THAN
SUBSTANTIAL EVIDENCE PROVING THE ADMINISTRATIVE GUILT OF PETITIONERS FOR
CONDUCT PREJUDICIAL TO THE BEST INTEREST OF THE SERVICE, THIS CONSIDERING THAT:
I.A
RESPONDENTS DID NOT CONDUCT THE REQUIRED DETAILED
ENGINEERING.
I.B
RESPONDENTS ISSUED A FALSE CERTIFICATE OF COMPLETION.
I.C
RESPONDENTS DID NOT CONDUCT THE REQUIRED ACTUAL
INSPECTION.
II.
THE FINDINGS OF THE OFFICE OF THE OMBUDSMAN DESERVE
GREATER WEIGHT, AND MUST BE ACCORDED FULL RESPECT AND CREDIT.[46]
Petitioner
contends that respondents neglected to perform a duty incumbent upon them. They
did not specify the station limits of the concreting project (in km); when they
agreed with the contractor that the project would be from Sum-ag to Caliban
Bridges, they again did not specify the station limits or the length of the
road between the two bridges. As alleged in Chan’s complaint, respondents did
not conduct the detailed mandatory engineering requirement prescribed by the Implementing
Rules of Presidential Decree No. 1594. Had a detailed engineering plan been
conducted, then the true station limits of the project would have been known to
respondents from the very start. Further, respondents’ defense of honest
mistake was belied by the fact that, while they issued a certificate of 100%
completion, the project was, in fact, still incomplete. The claim of respondents
that they conducted an initial survey and discovered that the project from
Sum-ag to Caliban Bridges was finished was not supported by evidence. Granting
that an initial survey had really been conducted, respondents should have known
before executing the contract for the project and awarding the same to King the
very scope of the project vis-à-vis
the stipulated items of work. Petitioner insists that respondents did not
really conduct an initial survey and they designated the start and end of the
project by mere guess work. The records further reveal that an additional work
order was issued by the Office of the District Engineer, where there was a
reduction of the items of work in the original contract. Petitioner stresses
that respondents realized that there was an excess in the quantity required to
concrete the road from the Sum-ag to the
Petitioner
insists that respondents did not actually inspect the project; the actual
accomplishment of the contractor was not checked or inspected in relation to
the quantities stated in the contract. Had an actual inspection been made, then
no error should have been committed. It further contends that the government
sustained injury from the time the project was certified as 100% complete up to
the actual discovery of the deficiency and the resumption of work, and for
this, respondents must be accountable.
Petitioner claims that the doctrine
in Arias v. Sandiganbayan[48] could not be invoked by respondents, as
they rest on different facts. Petitioner’s findings must likewise be given greater
weight and accorded full respect and credit.
For
their part, respondents counter that the sworn statement and the subsequent
joint supplemental complaint filed by Chan were hearsay, inadmissible in
evidence, as the affiants were not presented to identify their statements. They
cite the ruling of this Court in Tapiador
v. Office of the Ombudsman[49] to
support their contentions. Respondents further insist that the integrity and the
credibility of the complainants were highly questionable and tainted with
hatred, malice and bad faith, motivated as they were by hatred for respondents for
not having been given construction projects. They point out that Chan was also
of questionable character, having been dismissed from the police service for
grave misconduct (extortion).
Respondents
contend that they conducted the required detailed engineering survey of the
project: A station limit of 2 km. and 673 m. was also specified in the
engineering design/plans,[50] and
a program of works and detailed estimates were also prepared and approved. They
maintain that, per
the previous survey, the coverage of the project was from the Sum-ag to the Caliban
Bridges; hence, the Accomplishment Report and Certificate of Completion, which respondents
Maravilla and Javellana signed on
The
petition is meritorious.
This Court is to resolve the issue of
whether or not the Decision of the CA granting respondents’ petition for certiorari is erroneous, an issue which is
factual in nature.
Under Rule 45 of the Rules of Court,
only questions of law may be raised,[51] since
the Court, after all, is not a trier of facts.[52]
Unless for exceptional reasons, It is not to review the evidence on record and
assess the probative weight thereof.[53] However,
factual issues may be delved into and resolved where, as in this case, the
findings and conclusions of the Office of the Ombudsman in its decision are frontally
inconsistent with those in the assailed Decision and Resolution of the CA.[54]
Contrary
to the contention of respondents, the findings of the petitioner in its
decision were based on the records of the 1st Engineering District
of the DPWH and their (respondents’) admissions, and not merely on the allegations
in the Complaint-Affidavit and Supplemental Affidavit of Chan and his counsel.
The
parties, including the CA and the DPWH, have no dispute on the following basic
facts: the project was to start from the Sum-ag Bridge to a distance of
1,341.75 sq. m. beyond the Caliban bridge; on April 3, 2001, respondents
Maravilla and Javellana signed an Accomplishment Report in which they stated
that, after their inspection of the project, King had accomplished 95% of the
project. Respondents Maravilla and Javellana likewise signed a Certificate of
Completion, stating that they had inspected the project and found it 100%
completed as per approved plans and specifications of the Program of Work. It was also recommended that the balance of
the project price of P672,862.00 be paid to King. Respondents Maravilla,
Javellana and Tongson approved the release of P672,862.00. As ruled by petitioner,
as of
The
CA and the DPWH, however, concluded that the deficiency in the project as of
We
agree with petitioner’s contention that the deficiency in the project was
caused by respondents’ failure to state in their surveys, designs and program
of work, the station limits of the project. According to the Implementing Rules
and Regulations (IRR), implementing Presidential Decree (P.D.) No. 1594:
1. No
bidding and/or award of contract for a construction project shall be made
unless the detailed engineering investigations, surveys and designs for the
project have been sufficiently carried out and duly approved in accordance with
the standards and specifications prescribed by the Head of
office/agency/corporation concerned or his duly authorized representatives.
2.
Detailed engineering shall proceed only on the basis of the feasibility or
preliminary engineering study made which establishes the technical viability of
the project and conformably to land use and zoning guidelines prescribed by
existing laws. The findings contained in the feasibility study, if undertaken
for the project, shall be examined. If, in the course of [the] exercise, it is
found that changes would be desirable in the design standards of principal
features, as proposed, specific recommendations for such changes shall be
supported by justifications, including their effects on the cost, and (if
necessary) the economic justification.
3. A
schedule of detained engineering activities shall include the following:
a. Survey
b. Site Investigation
c. Soils and Foundation Investigation
d. Construction Materials Investigation
e. Preparation of Design Plans
f.
Preparation of Technical
Specifications
g. Preparation of Quantity and Cost Estimates
h. Preparation of Program of Work
i.
Preparation of
Proposed Construction Schedule (and estimated Cash Flow for Projects with
Schedule over Six (6) Months
j.
Preparation of
Site or Right-of-Way Plans including Schedule of Acquisition
k. Preparation of Utility Relocation Plan
l.
Preparation and
Submission of Design Report
m. Environmental Impact Statement for Critical Project as
defined by the Department of Environment and Natural Resources (DENR)
n. Preparation of minimum requirements for a construction
Safety and Health Program for the project being considered
o. Preparation of Bid/Tender Documents
4. Work under detailed engineering shall include but
not necessarily be limited to the following:
a.
Design Standards – Design standards shall be in accordance with appropriate
standards and accepted detailed engineering practice adopted by the
office/agency/corporation concerned. Design standards for structures shall take
into account, among other things, the seismicity of the area to determine the
optimum safety of structures and to minimize possible earthquake damage.
b.
Field Surveys and Investigation –Necessary field surveys which may include
aerial, hydrographic, topographic, hydrologic sub-surface, monumenting
and other surveys shall be carried out in accordance with the design,
guidelines, criteria, and standards adopted by the office/agency/corporation
concerned. All survey and investigation works shall be prepared in a manner
satisfactory to carry out accurate design and production of plans.
c. Contract
Plans – The following plans shall be prepared for each construction contract in
accordance with guidelines and standards adopted by the
office/agency/corporation concerned, incorporating at least the following:
(1) Site development plan
(2) Plans and profile sheet
(3) Typical sections and details
(4) Drainage details where applicable
(5) Structural plans at appropriate scales indicating all
details necessary in order that the complete structure can be set out and
constructed
(6) Other details which may be required by the Head of
office/agency/corporation
d.
Quantities – All construction quantities shall be computed to a reasonable
accuracy of plus or minus fifteen percent (15%).
e. Special Provisions – Specifications shall be
prepared for specific terms of work or methods of construction, measurement and
payment under each contract, which are not covered by Standard Construction and
Material Specifications adopted by the office/agency/corporation concerned.
Obviously,
respondents failed to comply with these rules. If they had so complied, they
would have known that, as of
Respondents’ failure to comply with P.D.
No. 1594 cannot be trivialized and classified as a mere oversight. At the very
least, it constitutes neglect of duty. It must be stressed that respondents were
mandated to comply with P.D. No. 1594 to insure that the terms and conditions
of the contract are clear and unambiguous and, thus, prevent damage and injury
to the government, and the consequent prejudice to the beneficiaries of project
like the commuters and other road users.
It bears stressing that the cost of the project was no less than P13,457,240.00.
The concreting had to be properly made especially considering that the Bacolod
City-Murcia-D.S. Benedicto-San Carlos City is a national road used by commuters
and those engaged in commerce in the two cities.
We also sustain the contention of petitioner
that the error and the deficiency could have been avoided had respondents been
prudent enough to conduct an actual and thorough inspection of the project. As engineers and employees of the DPWH, they are
expected to render public service with utmost responsibility, integrity,
loyalty, and efficiency.[55] Respondents
in this case fell short of the expectation and trust which the public had a
right to expect of them.
Respondents further failed to prove
their contention that per surveys, designs and program of work, the length of
the project was measured to be 2,673.00 m, from the Sum-ag Bridge to the Caliban
Bridge; that the station limit specified in the engineering design/plan was
from a distance of two km and 673 m; and that the road structure had an initial
length of 2,673.00 m. They inexplicably failed to present the surveys, designs
and specifications in the Office of the Ombudsman as evidence during the
investigation. If they had done so, they could have established the factual
basis for their claim that respondents Maravilla and Javellana had signed the
Certification and Accomplishment Report on
It bears stressing that even the
Report of the Fact-Finding Team to the DPWH Regional Director declared that
“this project did not specify the station limit.” This finding of the team
frontally belies respondents’ claim that, per their surveys and designs, the
station limit had been specified.
The inceptual neglect of respondents
was compounded when respondents Maravilla and Javellana falsely certified, on P608,634.25, per request of
King, despite their knowledge that the project was not yet 100% complete. We note that respondents Oropel and Tongson alleged
that they allowed payment of the balance of P608,634.25 despite the
deficiency considering that 95% of the
project had been accomplished; that it could be considered substantial
compliance with the undertaking of the contractor under the contract; and for
humanitarian reasons since the value of the deficiency was less than the 10%
retention money. This argument, however, is belied by the evidence on record, hence,
totally unacceptable. Respondents Maravilla and Javellana certified that the
project was 100% complete, not merely substantially complete. Respondents
Tongson and Oropel approved the payment of the last tranche despite the falsity
of the Report and Certification of respondents Maravilla and Javellana. There
is, likewise, no showing in the records that the contractor pleaded for
respondents Maravilla and Javellana, for humanitarian reasons, to falsify their
Report and Certification so that the last payment could be made.
Respondents must be reminded that government
funds must be disbursed only under the terms of the contract and upon
compliance with the requirements provided by law and the pertinent rules and
regulations.
Respondents Maravilla and Javellana
cannot feign ignorance of the fact that, as of April 3, 2001, only 80% of the
project had been completed, since Oropel admitted the same in his April 12, 2002
letter to the Graftwatch, where he stated that although the contractor had
completed only 95% of the project, he and Tongson, nevertheless, allowed
payment of the last tranche because of their belief that the project was
already substantially completed, and the 10% retention was more than sufficient
to answer for the deficiency of the project. It was precisely because of
Oropel’s and Tongson’s admission that prompted Chan to file his complaint
against respondents. Respondent Oropel
reiterated his claim in his counter-affidavit and further averred that it was a
common practice in the construction industry that when a project is 95%
complete, the same is considered as substantially completed, and that the
processing of the full payment of the contract price may be given due course. The
claim of Oropel is inconsistent with that of respondents Maravilla, Javellana, and
Tongson, in their respective counter-affidavits, that they believed in good
faith that, as of
Respondent Oropel’s claim of
substantial compliance has to be rejected in light of the Implementing Rules
and Regulations of P.D. No. 1594, which pertinently provides as follows:
CI 7 - CONTRACT COMPLETION
1. Once the project reaches an
accomplishment of 95% of the total contract amount, the government may create
an inspectorate team to make preliminary inspection and submit a punch-list to
the contractor in preparation for the final turnover of the project. Said
punch-list will contain, among others, the remaining works, work deficiencies
for necessary corrections, and the specific duration/time to fully complete the
project considering the approved remaining contract time as of the date of
contract suspension. This, however, shall not preclude the government’s claim
for liquidated damages, nor the contractor’s claim for incentive bonus, as the
case may be.
In his Counter-Affidavit, Oropel stated
that a punch-list was prepared prior to the payment of the last tranche on
The project was, indeed, eventually completed and, as
stated by the COA and the DPWH Fact-Finding Team, the government did not suffer
any losses,[56] since
respondents discovered the error before the 10% retention money was remitted to
the contractor. However, such facts by themselves do not absolve respondents
from administrative liability. At best, the same merely mitigates their
administrative liability. It must be stressed that the project remained
unfinished for two years because of respondents’ neglect. Respondent Oropel
admitted as much to the Bacolod Graftwatch in his
During
the intervening period therefor, from April 2001 up to
Evidently, Engr. Jose C. Maravilla and Engr. Jaime S.J. Javellana, on orders of their supervisors
District Engineer Rogelio Q. Tongson and Asst. District Engineer Sanny Boy
Oropel inspected the work accomplishments of Korona Construction and reported
that the project has been completed. It turned out that there was still a 20%
work deficiency in the project. They admitted that there was an error in the
computation of the area coverage of the project from
had the
said respondents prudently inspected and assessed the work accomplishment of
Korona Construction as against the project specifications. This, they failed.
Respondents’ failure to take such step has resulted in the delay in the actual
completion of the project and in the use thereof by the public. The
irregularity drew the attention of the media and the public, thus casting a bad
image to the public service.
It is
a thin excuse for the said respondents to interpose the defense that the error
in the computation of the area coverage of the project should not constitute an
administrative offense. While such error was not done in bad faith, the fact,
however, remains that being seasoned engineers at the DPWH and possessor of the
bid documents, they could have determined this irregularity earlier and avoided
it. Such neglect of duty proved to be
detrimental and prejudicial to their agency. The fact that they have remedied
the work deficiency will not exculpate them from administrative liability, but
such corrective measure can be made the basis of a mitigating circumstance.[59]
The
doctrine that was laid in the cited Arias
Case is completely inapplicable herein. In Arias, the transaction, including the falsification of the tax
declaration, was done before petitioner therein joined the
The facts are different in this case.
Respondents were direct participants in the project, not only from the time the
contract was awarded to Korona, but even up to the time the voucher for the
release of the full payment was made. Respondents were even the ones who actively
communicated and dealt with the contractor of the project. They were therefore
fully aware of the specifics of the concreting project, and cannot validly claim
that they merely signed the papers and relied on the representations of their
subordinates.
Under
the Civil Service law and rules, there is no concrete description of what specific
acts constitute the grave offense of conduct prejudicial to the best interest
of the service.[60] Considering
all the cogent facts and circumstances obtaining in this case, including the
mitigating circumstances, we find and so resolve that the respondents are
guilty of simple neglect of duty, a less grave offense punishable by suspension
for one (1) month and one (1) day to six (6) months for the first infraction.
The failure to use reasonable diligence in the performance of officially-
designated duties has been characterized as simple neglect of duty.[61]
As
a final note, let it be emphasized that when an officer or employee is disciplined, the object
sought is not the punishment of such officer or employee but
the improvement of the public service and
the preservation of the public’s faith and confidence in the
government.[62]
IN LIGHT OF ALL THE FOREGOING, the petition is GRANTED.
The Decision of the Court of Appeals in CA-G.R. SP No. 84694 is REVERSED and SET ASIDE. The decision of the petitioner in
OMB-V-A-02-0614-K is REINSTATED, with the MODIFICATION that respondents are found administratively liable for
neglect of duty, and are hereby suspended for three (3) months without pay.
SO ORDERED.
ROMEO J. CALLEJO, SR.
Associate Justice
WE
CONCUR:
Chief Justice
Chairperson
CONSUELO YNARES-SANTIAGO MA. ALICIA AUSTRIA-MARTINEZ
Associate Justice
Associate Justice
Associate Justice
Pursuant to Section 13, Article VIII of the
Constitution, it is hereby certified that the conclusions in the above decision
were reached in consultation before the case was assigned to the writer of the
opinion of the Court’s Division.
ARTEMIO
V. PANGANIBAN
Chief
Justice
[1] Penned
by Associate Justice Pampio A. Abarintos, with Associate Justice Mercedes Gozo-Dadole (retired) and Vicente L. Yap, concurring; rollo, pp. 43-50.
[2] Rollo, p. 397.
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
[17]
[18]
[19]
[20]
[21]
[22]
[23] Id at 369.
[24]
[25]
[26]
[27]
[28]
[29]
[30]
[31]
[32]
[33]
[34]
[35]
[36] Id at 241.
[37]
[38]
[39]
[40]
[41]
[42] Id at 50.
[43]
[44]
[45]
[46] Id at 18-19.
[47]
[48] G.R.
Nos. 81563 and 82512,
[49] G.R.
No. 129124,
[50] Id. at 299.
[51] Desierto v. Ocampo, G.R. No. 155419, March 4,
2005, 452 SCRA 789, 799.
[52] Nicolas v. Desierto, G.R. No. 154668, December
16, 2004, 447 SCRA 154, 156.
[53] Heirs of Ernesto Conahap v. Heirs of Prosperador Regaña, G.R. No. 152021, May 17, 2005, 458 SCRA 741, 747.
[54] See Desierto v. Ocampo, supra note 51, at 800.
[55] The Constitution, Article XI, Section 1.
[56] Rollo, p. 305.
[57] Supra note 55.
[58] Biteng v. Department of Interior and Local
Government (Cordillera Administrative
Region), G.R. No. 153894,
[59] Rollo, p. 239.
[60] Philippine Retirement Authority v. Rupa, 415
Phil. 713, 720 (2001).
[61] See Ayo v. Violago Isnani, A.M. No.
RTJ-99-1445,
[62] Civil Service Commission v. Cortez, G.R.
No. 155732,